Transportation Matters in Iowa | Blog

Print Friendly and PDF

Up to the challenge – keeping traffic moving on Iowa 2 in flood-ravaged SW Iowa

02/17/2020

47494974811_4cf7119d6e_5kWhen the flooding started in Southwest Iowa in March 2019, few people expected the water to rise and fall relatively quickly, as it did during the 2011 floods. The cause of this round of flooding was complicated with snowmelt runoff from the north, heavy spring rains, and swollen tributaries feeding the Missouri River.  

Nearly a year later, water still inundates a significant portion of several Southwest Iowa counties. Last Spring's heavy rainfall caused both the Missouri River and the Platte River that feeds it to swell, breaking through an intricate system of levees. With the levee system breached, powerful water ran freely through farmlands, towns, and the transportation system, impacting both state and county road and railroad lines. Local citizens were forced to find creative ways to get where they needed to go, often adding hours to each day’s commute. With more flooding predicted for Spring 2020, the Iowa DOT has been working non-stop on projects designed to reduce the traffic impacts more flooding could bring. One such project is on Iowa 2 near Nebraska City.

Map
Iowa 2 in this area is a four-lane roadway connecting Fremont County, Iowa to Nebraska City, Nebraska.

The situation in 2019

By the summer of 2019, Governor Kim Reynolds and her staff, working with surrounding state governors, surveyed the area and began collaborating closely with the Army Corps of Engineers, the Iowa Department of Transportation, and other groups with the ability to impact the situation. One specific area of concern is on Iowa 2 linking Iowa and Nebraska at Nebraska City.

6-26-19 Iowa 2 west of I-29 flooding
Raging flood waters destroyed parts of Iowa 2 in SW Iowa last Spring.

“One specific challenge to the Iowa DOT was to find a way to remove the pinch point Iowa 2 creates on the levee system west of I-29. In this section of the river, the rock bluff on the Nebraska side and the roadway embankment on the Iowa side create a narrow opening. The constriction increases the velocity in which the water flows through this section of river which elevates the risk of levee damage,” said Jeremy Vortherms, an Iowa DOT engineer in the Project Management Bureau.

The solution included the construction of a pair of bridges on Iowa 2 to allow water to flow through a wider opening at a reduced velocity during flooding events. Vortherms said, “Mother Nature will always bring unique weather events that are difficult to solve, but with the historical data we have for this area, we were confident these twin bridges would provide a benefit to the levee and transportation systems, and to the people who rely on them.”

The project included reconstruction of approximately 0.8 miles of the highway, including the construction of two 1,200-foot bridges (one for each direction of travel) and setting back a portion of the existing levee.

The solution is realized

Iowa DOT engineers Paul Flattery and Kelly Bell were tasked with designing the roadway around the structures. Consultant designers completed the bridge and levee portions of the project. With all partners working together, two-way traffic was shifted onto the new eastbound bridge on Dec. 6, 2019, a mere five months after the contractor was selected. The westbound bridge is now under construction and expected to be completed by the fall of 2020. Vortherms said, “We saw the importance of getting that bridge completed quickly.  In late December, water started flowing against the new levee and under the bridge due to continued flooding in the area.”

Vortherms continued, “The project goal to allow water to flow under at least one of the new bridges by spring 2020 has been accomplished. Everyone involved in the project understood the urgency of getting traffic moving in this area by this spring and pulled it together in very quickly. With our top-notch team putting together a simple, yet effective plan, that allowed a motivated contractor to get one side completed and have construction on the other side well underway.”

(123) WB Bridge - East End
With floodwater still impacting the area, two-way traffic is flowing on the completed westbound bridge. The two lanes of the eastbound side are expected to be completed later this year.

One key to success for this project - teamwork. Vortherms said, “I really can’t stress enough how the open communication, collaboration, and cooperation between all entities involved made this project work so well. Nine months ago we were issued a challenge to find a solution to the pinch point problem in this area and we met that challenge together.”

While this specific project dealt with one of the flood-related issues in Southwest Iowa, Vortherms cautions that there is still a lot of work to be done. “Eastbound Iowa 2 remains damaged east of the new bridge, reducing it to one lane in each direction in the westbound lanes. Solutions to resolve the issue of water overtopping the road in that area are being explored and a project is expected to be introduced later this year.


Verify your Comment

Previewing your Comment

This is only a preview. Your comment has not yet been posted.

Working...
Your comment could not be posted. Error type:
Your comment has been posted. Post another comment

The letters and numbers you entered did not match the image. Please try again.

As a final step before posting your comment, enter the letters and numbers you see in the image below. This prevents automated programs from posting comments.

Having trouble reading this image? View an alternate.

Working...

Have a comment?

Add your comment



Iowa highway in the evening